India Bharatmala audit: Phase I findings and response
- Auditor
- Comptroller and Auditor General of India
- Report date
- 10 August 2023
- Subject
- Bharatmala Pariyojana Phase I
- Audited bodies
- Road ministry, NHAI and NHIDCL
- Status
- implementation and monitoring continuing
- Last checked
- 20 October 2026
What the audit found
The Union government approved Bharatmala Phase I in 2017 for 34,800 kilometres of roads from 2017-18 to September 2022, at an estimated ₹5.35 lakh crore 1,3.
The CAG found gaps in corridor planning, project appraisal and the selection of works placed under the programme. It said the ministry had no long-term perspective plan or detailed action plan tied to stated outcome indicators 1.
The report recorded that 38.79 percent of the approved length was complete by March 2023. It found projects from the earlier National Highways Development Project had been added without first resolving the obstacles that had delayed them 1.
The audit examined route substitution and appraisal issues, including parts of the Delhi-Vadodara Expressway. It issued 41 recommendations covering planning, approvals, tendering, contract management and outcome monitoring 1.
The official response
Replies from the Ministry of Road Transport and Highways, NHAI and NHIDCL appear beside the findings in the CAG report. The agencies accepted some recommendations, described later controls and disputed parts of the audit analysis 1.
The ministry said project choices had to account for traffic, network links and implementation needs. The CAG retained findings where it considered the replies or records insufficient 1.
Parliament
The CAG sent the report to the government on 26 July 2023, and it was tabled in Parliament on 10 August 2023 2. Tabling placed the findings and agency replies in the public parliamentary record.
No later parliamentary committee report closing all 41 recommendations was identified in the official sources reviewed. Tabling the audit did not itself settle each project-level finding.
Follow-up audits and recommendations
The CAG called for a long-term national-highway plan, clearer criteria for programme inclusion, documented appraisals, stronger tender checks and monitoring against intended outcomes 1.
In June 2025 the road ministry published a mechanism for monitoring outcome parameters for capacity-augmentation projects, including Bharatmala Phase I 4. That later document addresses an area raised by the audit, but it is not a CAG closure assessment for all 41 recommendations.
Courts, tribunals and investigations
No court judgment deciding the CAG's programme-wide findings was identified in the official sources reviewed. Individual road projects may have separate land, environment or contract proceedings outside the scope of this page.
The audit concerns programme governance, procurement and delivery. It does not make a criminal finding against the ministry, an implementing agency or a contractor 1.
Where it stands now
Bharatmala Phase I remained an active road programme after the audit period. The ministry's 2025 monitoring document shows that outcome measurement continued to be developed 4.
The official record reviewed does not contain a single recommendation tracker showing which of the CAG's 41 recommendations have been accepted, implemented or closed. The case remains open for documentary follow-up.
Timeline
| Date | Event |
|---|---|
| 2017 | The Union government approved Bharatmala Phase I 1,3. |
| September 2022 | The original programme period ended 1. |
| March 2023 | The CAG recorded 38.79 percent of approved length as complete 1. |
| 26 July 2023 | The report was sent to the government 2. |
| 10 August 2023 | Report No. 19 of 2023 was tabled in Parliament 2. |
| 6 June 2025 | The ministry published its outcome-monitoring mechanism 4. |
Common questions
How large was Bharatmala Phase I?
It covered 34,800 kilometres at an approved estimate of ₹5.35 lakh crore 1,3.
How many recommendations did the CAG make?
The report contained 41 recommendations 1.
Were all recommendations closed?
No official CAG item-level closure record was identified in the sources reviewed.
Audit cases move on. Each page shows the date we last checked it. Spotted an error or a newer official record? Email [email protected] with the official link.
Sources
- Comptroller and Auditor General of India: Bharatmala Phase I report
- CAG: Report No. 19 of 2023 record
- Ministry of Road Transport and Highways: Bharatmala Phase I overview
- Ministry of Road Transport and Highways: Bharatmala Phase I documents
Related
- Australia Inland Rail audit: findings and project reset
ANAO findings on Inland Rail procurement and governance, the official response, parliamentary review and the later project reset.
- EU high-speed rail audit: findings and later progress
European Court of Auditors findings on high-speed rail planning, costs and cross-border links, with Commission replies and later audits.
- UK hospital PFI audit: findings and contract status
NAO and Parliament findings on hospital PFI contract management, the government response and later preparations for contract expiry.
- Australia Future Submarine audit and programme outcome
ANAO findings on the French-designed Future Submarine programme, Defence's response, Parliament and the later nuclear-powered pathway.