Australia Inland Rail audit: findings and project reset

Last checked: 20 October 2026 · Audit cases

The Australian National Audit Office found that Inland Rail's pre-construction procurement needed greater focus on value for money 1. Seventeen percent of its 54-item sample was sole sourced, with weak systems, incomplete records and unexplained contract variations 1. ARTC agreed in principle with the three recommendations, with one qualification 1. A 2023 independent review led to new governance arrangements 3, and in May 2026 the government limited current construction to Beveridge to Parkes 4.
Auditor
Australian National Audit Office
Report date
27 September 2017
Subject
Inland Rail pre-construction programme
Contractor
Australian Rail Track Corporation
Status
follow-up pending
Last checked
20 October 2026

What the audit found

The ANAO examined governance, grant administration and procurement during Inland Rail's pre-construction phase. The planned Melbourne to Brisbane route covered about 1,700 kilometres, and the Commonwealth had provided $300 million for pre-construction work 1.

The audit found that governance and grant administration were broadly appropriate, but a ministerially requested funding agreement was not completed on time. It said procurement needed greater focus on competition, transparency and value for money 1.

ANAO tested 54 procurements from April 2014 to October 2016. Seventeen percent were sole sourced, mainly early in the programme. It found unexplained contract-value variations, work beginning before contracts were executed and incomplete records about probity advice 1.

The audit found that ARTC's existing technology, procurement and document-management systems did not meet the programme's needs. Later procurements showed better competition and documentation after ARTC introduced new systems and procedures 1.

The official response

ARTC agreed in principle with the risk-management recommendation and said work was under way on records management. It agreed in principle, with a qualification, to the procurement recommendation 1.

ARTC said uncertainty over funding, timing and delivery responsibility affected early procurement. It pointed to later competitive sourcing, updated procedures, system changes and planned independent contract review 1.

The infrastructure and finance departments supported the recommendations. The infrastructure department said it expected the ARTC board to report regularly to shareholder ministers on implementation 1.

Parliament

The Auditor-General's report was prepared for Parliament and published on 27 September 2017 1. A later Senate inquiry examined project management, the business case, route selection, cost and community consultation 2.

The Senate committee called for a new business case and further scrutiny. The government response did not support every recommendation, including the proposed form of the business-case review 2.

Follow-up audits and recommendations

The 2017 audit made three recommendations on risk management, records and procurement controls 1. A separate independent review completed in 2023 made 19 recommendations on scope, cost, governance and delivery. The government accepted all 19 in full or in principle 3.

The government created Inland Rail Pty Ltd as an ARTC subsidiary with its own board and issued a new statement of expectations in 2023 3. ANAO began another performance audit in 2026 on delivery-risk management, with tabling planned for February 2027 5.

Courts, tribunals and investigations

No court judgment deciding the 2017 ANAO findings was identified in the official sources reviewed. The audit and later reviews concern administration, procurement, cost and delivery 1,3.

The cited sources do not establish that an ARTC officer, official or supplier committed a crime. Contract and route disputes outside the audit's scope are not treated as findings on this page.

Where it stands now

In May 2026 the government said independent cost work put full Melbourne to Brisbane delivery above $45 billion and no earlier than 2036. It chose to complete Beveridge to Parkes by the end of 2027 and preserve the corridor north of Parkes 4.

The new ANAO audit was still collecting evidence in October 2026. Its stated questions cover the adequacy of risk frameworks and the management of delivery risks 5. The 2017 findings now sit within a longer project reset rather than a completed recommendation record.

Timeline

DateEvent
2014The Commonwealth provided $300 million for pre-construction work 1.
27 September 2017ANAO published Report No. 9 of 2017-18 1.
2021The Senate inquiry reported on Inland Rail management 2.
6 April 2023The government accepted all 19 independent-review recommendations in full or in principle 3.
June 2023Inland Rail Pty Ltd was established with a separate board 3.
6 May 2026The government limited present construction to Beveridge to Parkes 4.
February 2027The new ANAO delivery-risk audit is scheduled to be tabled 5.

Common questions

What did ANAO find about Inland Rail procurement?

It found insufficient focus on competition and value for money in early procurement, with later improvements 1.

Did ARTC accept the recommendations?

It agreed in principle with all three, adding a qualification to the procurement recommendation 1.

Will the full line be completed by 2027?

No. The current commitment is Beveridge to Parkes by the end of 2027 4.

Is another audit under way?

Yes. ANAO plans to table a delivery-risk audit in February 2027 5.

Audit cases move on. Each page shows the date we last checked it. Spotted an error or a newer official record? Email [email protected] with the official link.

Sources

  1. ANAO: Management of the Pre-construction Phase of Inland Rail
  2. Parliament of Australia: Inland Rail inquiry report
  3. Department of Infrastructure: response to the independent review
  4. Infrastructure Minister: Inland Rail consolidation, May 2026
  5. ANAO: Management of delivery risks for Inland Rail