UK hospital PFI audit: findings and contract status
- Auditor
- UK National Audit Office
- Report date
- 17 June 2010
- Subject
- Operational hospital PFI contracts
- Contractors
- Multiple PFI companies
- Status
- follow-up pending
- Last checked
- 20 October 2026
What the audit found
The NAO examined 76 operational hospital PFI contracts in England with a capital value of £6 billion. It focused on contract performance after hospital buildings opened, rather than the original decision to use private finance 1.
The report found that most contracts were well managed and met the value-for-money expectations set when signed. It found no evidence that bundling cleaning, laundry, portering and similar services into PFI was better or worse value than separate management 1.
Long-term risks remained. Nine contracts had less than 0.2 full-time-equivalent public staff assigned to contract management. Trusts had limited room to reduce index-linked payments, and the Department of Health lacked central portfolio data for benchmarking and intervention 1.
The official response
The government's 2011 Treasury Minute agreed with the call for continued central support and partly agreed with recommendations on maintenance tests and portfolio action. It cited a contract-review pilot, a best-practice model and support for NHS trusts 3.
The response said the Department of Health would work with trusts on future central support. Treasury planned to use lessons from a review of Queen's Hospital in Romford across the wider PFI portfolio 3.
Parliament
The Public Accounts Committee took evidence from officials and published PFI in Housing and Hospitals in January 2011. For hospitals, it repeated that most operational contracts met the original expectations, but pressed for data, maintenance tests, stronger bargaining and central support 2.
The committee treated local trusts as the day-to-day contract managers and central departments as portfolio stewards. Its recommendations sought clearer oversight of costs, performance and savings across the group of contracts 2.
Follow-up audits and recommendations
In 2020 the NAO examined PFI contract expiry across English public bodies. More than 700 UK PFI contracts were then operational, and the audit focused on skills, contract records, asset condition and service continuity as contracts end 4.
A 2021 Public Accounts Committee report said government had launched an expiry-support programme with contract health checks, training and expert support. It still found gaps in contract records and central data 5.
Courts, tribunals and investigations
No court judgment deciding the 2010 portfolio audit findings was identified in the official sources reviewed. Individual PFI contracts can produce disputes or litigation, but those records do not amount to a judicial ruling on this NAO report 1,4.
The sources record audit and parliamentary scrutiny. They do not establish criminal conduct by a trust, contractor or investor 1,2.
Where it stands now
The government announced in 2018 that it would stop using PFI for new projects. Existing contracts remained in force, with many approaching expiry and asset handback 4,5.
Later official work shifted from the 2010 question of day-to-day hospital contract performance to expiry readiness across sectors. No single official tracker closing every hospital recommendation was identified, so this case remains follow-up pending 3,5.
Timeline
| Date | Event |
|---|---|
| April 2009 | The portfolio contained 76 operational hospital PFI contracts with a £6 billion capital value 1. |
| 17 June 2010 | The NAO published its hospital PFI contract audit 1. |
| 18 January 2011 | The Public Accounts Committee published its report 2. |
| March 2011 | The government published its formal response 3. |
| October 2018 | The government announced that it would not use PFI for new projects 4. |
| 5 June 2020 | The NAO published its audit of PFI contract expiry 4. |
| 19 March 2021 | The committee reported on the expiry programme 5. |
Common questions
Did the NAO find every hospital PFI contract failed?
No. It reported that most operational contracts met the value-for-money expectations set when they were signed 1.
Did the government accept Parliament's recommendations?
It agreed with some and partly agreed with others, setting out contract-review and support work 3.
Are hospital PFI contracts still active?
Existing contracts continued after the 2018 decision to stop using PFI for new projects 4,5.
Audit cases move on. Each page shows the date we last checked it. Spotted an error or a newer official record? Email [email protected] with the official link.
Sources
- National Audit Office: hospital PFI contracts
- Public Accounts Committee: PFI in Housing and Hospitals
- HM Treasury: response to Public Accounts Committee reports
- National Audit Office: managing PFI contract expiry
- Public Accounts Committee: managing PFI contract expiry
Related
- NHS National Programme for IT: audits and final outcome
NAO reports, the Department of Health response, Parliament's recommendations, dismantling of the programme and the final benefits review.
- South Africa COVID-19 PPE audit: what happened next
AGSA findings on PPE procurement, official responses, parliamentary scrutiny, SIU investigations, recoveries and Special Tribunal cases.
- Universal Credit audit: what happened after the 2013 report
NAO findings on Universal Credit from the 2013 programme reset through the 2024 migration review and current audit position.
- What happens after a government audit: the stages from report to outcome
The stages after a public audit report: management response, public accounts hearings, tracking, follow-up audits, referrals, recovery and courts.